Decide

Funding, soberly

In North Rhine-Westphalia two programmes have a funding provision for shading. Both end on 31 December 2026.

Here you find the wording of the guidelines – and the one rule most applications fail on.

The mistake that costs the funding

Every programme listed excludes funding if the project began before approval – and placing the order already counts as beginning. KfW puts it most clearly: Als Vorhabenbeginn gilt der Abschluss eines der Ausführung zuzurechnenden Lieferungs- oder Leistungsvertrags. (Concluding a supply or service contract attributable to execution counts as the start of the project.) First the application, then the approval, then the order.

Nordrhein-Westfalen

Two programmes for NRW

Both run until 31 December 2026 and contain a funding provision for shading. Which one applies depends on the applicant’s legal form.

Klimaanpassung.Kommunen.NRW

For municipalities, associations, registered clubs and foundations. Provision: Bau von Verschattungsanlagen und Maßnahmen zum Schutz vor UV-Strahlung.

Usually 80 % of eligible costs, up to 90 % for municipalities in budget emergency. Minimum for municipalities €12,500, project volume under €200,000. Deadline 31 Dec 2026, 2 pm.

Klimaanpassung.Unternehmen.NRW

For SMEs and municipal companies – housing companies, hospitality, retail, municipal utilities. Provision: Verschattungselemente.

Up to 60 % of eligible costs, minimum €2,000 net. Applications until 31 Dec 2026.

How we structure the quotation for this

Both guidelines exclude certain components: seating is not eligible under the municipal programme, purely technical measures are not eligible under the business programme. Our quotations therefore list the bench and the sensors as separate items, so neither jeopardises the application for the rest.

Neither guideline expressly settles whether a module not fixed to the ground counts as a shading installation. We have asked the programme administrator in writing and will publish the answer here. Until then we do not say a Stadthain is eligible in NRW – only that the provision fits.

Outside NRW

Three states with fitting wording

If you procure outside North Rhine-Westphalia: in these three states the text of the guideline covers the product category word for word.

Baden-Württemberg · KLIMOPASS

The “Förderbaukasten Blau-Grün” expressly includes im Raum freistehende Begrünungskonstruktionen abseits einer Fassade. Applications to L-Bank until 31 Dec 2026.

Rhineland-Palatinate · Stadt- und Dorfgrün

VV Stadt- und Dorfgrün no. 2.1.7 – the only German funding provision that names street furniture: Begrünung von Stadtbänken, Bushaltestellen, Schulhöfen, Fußgängerzonen. 80 % of eligible costs, minimum grant €20,000. Applications annually from 1 May to 30 June.

Bavaria · KommKlimaFöR 2026

Eligible: naturbasierte Beschattungen für öffentliche Plätze. Up to 50 %. Municipal enterprises are eligible too, i.e. municipally owned utilities. Runs until 31 Dec 2029.

Not a fit

Programmes that sound right and are not

Municipal courtyard, roof and façade greening programmes usually exclude containers. Cologne, for example: Pflanzkübel, Balkonbepflanzungen; Leverkusen: Maßnahmen, die auf das Aufstellen von Pflanzkübeln oder Ähnlichem beschränkt sind.

Also not a fit: KfW 444 (funds real tree planting with root trenches), progres.nrw (energy only) and the federal programme “Anpassung urbaner Räume” (deadline passed, minimum grant €500,000).

School and nursery grounds

We are not the right supplier for this. School ground programmes fund unsealing and real tree planting, not placed modules. A climbing frame on a children’s area will be climbed and falls under playground equipment requirements we do not meet. And the applicant must be the school authority, not the school. The first port of call here is a landscape architect.

Our role

What we do and do not do

We prepare the application documents: description of the measure, cost breakdown split by eligibility, impact justification, timetable, annexes. The applicant checks, completes and submits them. We are not funding consultants and do not submit on anyone’s behalf.